16 Jul
2016
16 Jul
'16
8:34 p.m.
Hi everyone, This is the fourth report for the 'Expand Nyx' project for GSoC 2016. I have been working on the following things since the past 2 weeks: * Added the history validation for the interpreter panel. * Added the tab completion for the interpreter panel. * Rebased code to include recent changes made by Damian. * Added some tests for the interpreter panel. The interpreter panel code ca be seen at: https://github.com/sammyshj/nyx/pull/12 In the next weeks, I will be adding rest of the tests for the interpreter panel and then start work on getting additional information provided by Onionoo. Hope everyone has a fun weekend! Thanks, Sambuddha