[or-cvs] r22061: {projects} update progress on the tasklist, and the gantt-chart (projects/todo)

Andrew Lewman andrew at torproject.org
Fri Mar 26 16:17:27 UTC 2010


Author: phobos
Date: 2010-03-26 16:17:27 +0000 (Fri, 26 Mar 2010)
New Revision: 22061

Modified:
   projects/todo/tpo-highlevel-tasklist.tjp
   projects/todo/tracking-gantt.pdf
Log:
update progress on the tasklist, and the gantt-chart 


Modified: projects/todo/tpo-highlevel-tasklist.tjp
===================================================================
--- projects/todo/tpo-highlevel-tasklist.tjp	2010-03-26 12:19:40 UTC (rev 22060)
+++ projects/todo/tpo-highlevel-tasklist.tjp	2010-03-26 16:17:27 UTC (rev 22061)
@@ -36,7 +36,7 @@
     start 2009-11-19
     effort 30d
     allocate andrew, volunteer, vendor
-    complete 80
+    complete 90
     }
   task op_two "Website Documentation Update" {
     start 2009-11-19
@@ -54,7 +54,7 @@
     start 2009-12-01
     end 2010-05-01
     allocate andrew, vendor
-    complete 20
+    complete 40
   }
   task op_five "Legal Directory" {
     start 2009-11-19
@@ -66,7 +66,7 @@
     start 2009-11-19
     end 2010-02-28
     allocate andrew, melissa, auditor
-    complete 95
+    complete 100
   }
   task op_seven "Tor Logo Store" {
     start 2009-11-19
@@ -106,9 +106,9 @@
   }
   task op_thirteen "Brochure" {
     start 2009-11-19
-    end 2010-02-28
+    effort 14d
     allocate karen
-    complete 75
+    complete 100
   }
   task op_fourteen "2010 Donation Drive" {
     start 2010-01-01
@@ -146,15 +146,9 @@
     allocate andrew, karen
     complete 100
   }
-  task op_twenty "Brochure" {
+  task op_twenty "10 Things Whitepaper" {
     start 2010-01-01
     effort 14d
-    allocate karen
-    complete 50
-  }
-  task op_twenty_one "10 Things Whitepaper" {
-    start 2010-01-01
-    effort 14d
     allocate roger, karen
     complete 80
   }
@@ -171,7 +165,7 @@
     start 2009-11-19
     end 2009-12-31
     allocate carolyn, volunteer
-    complete 85
+    complete 100
   }
   task tr_three "Arabic Translator" {
     start 2009-11-19
@@ -183,7 +177,7 @@
     start 2009-11-19
     end 2009-12-31
     allocate carolyn, volunteer
-    complete 75
+    complete 100
   }
   task tr_five "Chinese Translator" {
     start 2009-11-19
@@ -193,9 +187,9 @@
   }
   task tr_six "Spanish Translator" {
     start 2009-11-19
-    end 2009-12-31
+    effort 14d
     allocate carolyn, volunteer
-    complete 15
+    complete 50
   }
   task tr_seven "Automated Translator" {
     start 2009-11-19
@@ -205,9 +199,9 @@
   }
   task tr_eight "Farsi Translator" {
     start 2009-11-19
-    end 2009-12-31
+    effort 14d
     allocate carolyn, volunteer, karen
-    complete 35
+    complete 50
   }
 }
 
@@ -248,9 +242,9 @@
     }
     task rd_one_two "further research" {
       start 2009-11-20
-      end 2010-02-28
+      effort 45d
       allocate roger, volunteer
-      complete 10
+      complete 20
     }
   }
   task rd_two "NSF Research" {
@@ -258,13 +252,13 @@
     start 2009-11-20
     effort 45d
     allocate roger, andrew, melissa
-    complete 80
+    complete 100
   }
     task rd_two_two "Tor metrics research" {
       start 2009-11-20
       effort 60d
       allocate karsten, roger
-      complete 10
+      complete 25
     }
   }
   task rd_three "NRL Research" {
@@ -278,7 +272,7 @@
       start 2009-11-20
       end 2010-06-01
       allocate roger, volunteer
-      complete 50
+      complete 60
     }
   }
   task rd_four "Performance Improvements" {
@@ -292,13 +286,13 @@
       start 2009-12-14
       effort 5d
       allocate nick
-      complete 0
+      complete 30
       }
     task rd_four_three "Multithreaded Crypto-ops" {
       start 2009-12-14
       effort 15d
       allocate nick, steven
-      complete 0
+      complete 10
     }
   }
   task rd_five "Financial Cryptography Paper Revision" {
@@ -330,7 +324,7 @@
       start 2009-11-19
       effort 30d
       allocate steven
-      complete 5
+      complete 20
     }
     task rd_seven_four "Continuing Research into everyone as a relay" {
       start 2009-11-19
@@ -406,13 +400,13 @@
     start 2010-01-02
     effort 5d
     allocate karsten, roger
-    complete 80
+    complete 90
   }
   task m_eight "New Metrics Server Setup" {
     start 2010-03-01
-    effort 7d
+    effort 14d
     allocate karsten, andrew
-    complete 10
+    complete 20
   }
   task m_nine "Metrics Website Presentation" {
     start 2010-03-01
@@ -460,7 +454,7 @@
     start 2009-11-19
     effort 14d
     allocate mike
-    complete 75
+    complete 90
   }
   task lat_two "Connection rate limiting" {
     start 2009-11-19
@@ -610,7 +604,7 @@
     start 2009-11-19
     effort 30d
     allocate erinn, jacob
-    complete 60
+    complete 80
   }
   task pkg_seven "Nightly package builds" {
     start 2009-11-19
@@ -643,19 +637,19 @@
     start 2009-11-19
     effort 7d
     allocate nick, volunteer
-    complete 75
+    complete 90
   }
   task lb_two "Buffer events" {
     start 2009-11-19
     effort 7d
-    allocate nick, volunteer
-    complete 75
+    allocate nick, roger
+    complete 90
   }
   task lb_three "Buffer events merge to Tor" {
     start 2009-11-19
     effort 7d
-    allocate nick
-    complete 50
+    allocate nick, roger
+    complete 90
   }
 }
 

Modified: projects/todo/tracking-gantt.pdf
===================================================================
(Binary files differ)