[or-cvs] r21904: {projects} updated project status, updated gantt chart. (projects/todo)

Andrew Lewman andrew at torproject.org
Tue Mar 9 22:00:37 UTC 2010


Author: phobos
Date: 2010-03-09 22:00:36 +0000 (Tue, 09 Mar 2010)
New Revision: 21904

Modified:
   projects/todo/tpo-highlevel-tasklist.tjp
   projects/todo/tracking-gantt.pdf
Log:
updated project status, updated gantt chart.


Modified: projects/todo/tpo-highlevel-tasklist.tjp
===================================================================
--- projects/todo/tpo-highlevel-tasklist.tjp	2010-03-09 21:56:18 UTC (rev 21903)
+++ projects/todo/tpo-highlevel-tasklist.tjp	2010-03-09 22:00:36 UTC (rev 21904)
@@ -10,7 +10,7 @@
   }
 }
 
-resource carolyn "Carolyn" {limits{dailymax 4h}}
+resource carolyn "Carolyn" {limits{weeklymax 2h}}
 resource sebastian "Sebastian" {limits{dailymax 4h}}
 resource nick "Nick" {limits{dailymax 8h}}
 resource jacob "Jacob" {limits{dailymax 8h}}
@@ -24,7 +24,7 @@
 resource karsten "Karsten" {limits{dailymax 8h}}
 resource peter "Peter" {limits{dailymax 4h}}
 resource martin "Martin" {limits{dailymax 4h}}
-resource runa "Runa" {limits{dailymax 2h}}
+resource runa "Runa" {limits{weeklymax 8h}}
 resource vendor "Paid Vendor" {limits{dailymax 16h}}
 resource melissa "Melissa" {limits{dailymax 4h}}
 resource auditor "Auditors" {limits{dailymax 16h}}
@@ -34,15 +34,15 @@
 task op_main "Business Operations" {
   task op_one "Community Forums" {
     start 2009-11-19
-    end 2010-02-28
+    effort 30d
     allocate andrew, volunteer, vendor
-    complete 75
+    complete 80
     }
   task op_two "Website Documentation Update" {
     start 2009-11-19
     effort 3d
     allocate andrew, volunteer
-    complete 25
+    complete 30
   }
   task op_three "Package Naming Conversion" {
     start 2009-11-19
@@ -54,7 +54,7 @@
     start 2009-12-01
     end 2010-05-01
     allocate andrew, vendor
-    complete 15
+    complete 20
   }
   task op_five "Legal Directory" {
     start 2009-11-19
@@ -82,9 +82,9 @@
   }
   task op_nine "2009 Annual Report" {
     start 2009-11-19
-    end 2010-02-28
+    effort 14d
     allocate andrew, karen
-    complete 75
+    complete 80
   }
   task op_ten "Migrate wiki" {
     start 2009-11-19
@@ -132,11 +132,11 @@
     start 2009-11-19
     effort 5d
     allocate steven
-    complete 25
+    complete 30
   }
   task op_eighteen "Relay Advocacy" {
     start 2009-11-19
-    end 2010-01-31
+    effort 30d
     allocate jacob, andrew, roger, volunteer
     complete 30
   }
@@ -146,6 +146,18 @@
     allocate andrew, karen
     complete 100
   }
+  task op_twenty "Brochure" {
+    start 2010-01-01
+    effort 14d
+    allocate karen
+    complete 50
+  }
+  task op_twenty_one "10 Things Whitepaper" {
+    start 2010-01-01
+    effort 14d
+    allocate roger, karen
+    complete 80
+  }
 }
 
 task tr_main "Translations" {
@@ -187,8 +199,8 @@
   }
   task tr_seven "Automated Translator" {
     start 2009-11-19
-    end 2009-12-31
-    allocate carolyn, volunteer
+    effort 30d
+    allocate runa, volunteer
     complete 0
   }
   task tr_eight "Farsi Translator" {
@@ -216,11 +228,11 @@
     start 2009-11-19
     end 2010-02-28
     allocate melissa, andrew
-    complete 90
+    complete 100
   }
   task fin_four "Monthly Report Generation" {
     start 2009-11-19
-    end 2009-12-31
+    effort 30d
     allocate melissa
     complete 85
   }
@@ -244,9 +256,9 @@
   task rd_two "NSF Research" {
     task rd_two_one "NSF Contract" {
     start 2009-11-20
-    end 2010-02-15
+    effort 45d
     allocate roger, andrew, melissa
-    complete 75
+    complete 80
   }
     task rd_two_two "Tor metrics research" {
       start 2009-11-20
@@ -265,7 +277,7 @@
     task rd_three_two "Trust Metrics Research" {
       start 2009-11-20
       end 2010-06-01
-      allocate roger, karsten, volunteer
+      allocate roger, volunteer
       complete 50
     }
   }
@@ -285,7 +297,7 @@
     task rd_four_three "Multithreaded Crypto-ops" {
       start 2009-12-14
       effort 15d
-      allocate nick
+      allocate nick, steven
       complete 0
     }
   }
@@ -318,7 +330,7 @@
       start 2009-11-19
       effort 30d
       allocate steven
-      complete 0
+      complete 5
     }
     task rd_seven_four "Continuing Research into everyone as a relay" {
       start 2009-11-19
@@ -372,30 +384,42 @@
     allocate karsten
     complete 100
   }
-  task m_four "MaxMind GeoIP DB sync" {
+  task m_four "MaxMind GeoIP DB comparison" {
     start 2009-12-07
-    end 2009-12-31
+    effort 14d
     allocate karsten
     complete 25
   }
-  task m_five "DirAuth to DB Direct" {
-    start 2010-01-02
+  task m_five "Server Descriptor Aggregator" {
+    start 2010-03-01
     effort 14d
-    allocate karsten, volunteer
-    complete 0
+    allocate karsten
+    complete 75
   }
   task m_six "Weekly Bridge Stats" {
     start 2010-01-02
-    end 2010-02-28
+    effort 5d
     allocate karsten, roger
     complete 50
   }
-  task m_seven "Weekly TorPerf Stats" {
+  task m_seven "Daily TorPerf Stats" {
     start 2010-01-02
-    end 2010-02-28
+    effort 5d
     allocate karsten, roger
-    complete 50
+    complete 80
   }
+  task m_eight "New Metrics Server Setup" {
+    start 2010-03-01
+    effort 7d
+    allocate karsten, andrew
+    complete 10
+  }
+  task m_nine "Metrics Website Presentation" {
+    start 2010-03-01
+    effort 30d
+    allocate volunteer, karsten, andrew
+    complete 0
+  }
 }
 
 task torbutton "Torbutton Improvements" {
@@ -533,9 +557,9 @@
 task mobiletor "Tor on mobiles" {
   task mt_one "OrBot: Tor on Android" {
     start 2009-11-19
-    end 2010-02-28
-    allocate jacob, volunteer
-    complete 85
+    effort 30d
+    allocate jacob, volunteer, erinn
+    complete 90
   }
   task mt_two "Tor on Maemo" {
     start 2009-11-19
@@ -580,13 +604,13 @@
     start 2009-11-19
     effort 30d
     allocate erinn, jacob
-    complete 50
+    complete 25
   }
   task pkg_six "Tor Browser Bundle for Linux" {
     start 2009-11-19
     effort 30d
     allocate erinn, jacob
-    complete 50
+    complete 60
   }
   task pkg_seven "Nightly package builds" {
     start 2009-11-19